What does a city government actually buy when it procures a smart street lighting system? The equipment and the app are visible at the time of acceptance. Energy savings and the ability to detect malfunctions become apparent during operation—provided the city government has established in advance how it will measure them.
In November 2026, the European community Procure Innovation EU published Insight No18. Green and digital transition through PPI, a paper on how public procurement of innovative solutions can contribute to the green and digital transition.
The question posed by the document is worth incorporating into every procurement strategy that pursues such objectives. What outcome do we want to achieve for the public service, and what evidence will we use to show that we have achieved it? public-buyers-community.ec.europa.eu
Measurement starts before the procedure is launched
The European paper proposes four steps. The authority establishes the baseline, defines the expected outcome, links it to contractual performance indicators and, after implementation, evaluates the effects. The sequence matters. A reduction in consumption expressed as a percentage makes sense only if we know what consumption it is calculated against and under what conditions we compare the periods. public-buyers-community.ec.europa.eu
This is where the role of the department that will use the solution becomes visible. In the street lighting example, the technical department knows the network, the operating schedule and the history of malfunctions. The procurement department can turn these data, together with the technical department, into clear requirements, evidence for evaluating tenders and obligations that can be monitored during contract performance.
An example for the technical specifications and the contract
Suppose a city government aims to reduce the energy consumed by public lighting and to identify malfunctions faster. The two objectives can be pursued separately, even if they are met by the same system.
| What the city government is aiming for | What it sets before launch | What it verifies in operation |
|---|---|---|
| Reducing energy consumption | Baseline consumption for the lighting points included, the reference period and the lighting conditions that must be met | Measured consumption, compared for the same perimeter and equivalent operating conditions, according to the method set out in the contract |
| Detecting malfunctions faster | The types of malfunctions the system must detect, the reporting deadline and the testing method | The time between the occurrence of a detectable malfunction and the recording of the alert, verified through tests and event logs |
If the city government changes the lighting schedule or extends the network, these changes must be taken into account before the difference in consumption is attributed to the solution purchased. Likewise, an alert sent quickly proves that the system can report the malfunction within the required time. To find out whether residents also benefit from faster interventions, the city government must track the time to repair separately.
What we require, what we score and what we track in the contract
In the technical specifications, Article 156(1)(a) of Law No. 98/2016 allows technical specifications to be formulated in terms of performance or functional requirements, including environmental characteristics. The parameters must be precise enough for tenderers to understand the subject matter of the contract and for the authority to be able to award it. In our example, the city government can describe the level of illumination and the monitoring performance sought, leaving economic operators room to propose the technical solution.
In evaluating tenders, if the authority awards points for superior performance, Article 189(2) of the same law requires provisions that allow effective verification of the information supplied by tenderers. For example, if the score depends on the tendered energy consumption, the documentation must make it possible to compare the values under common conditions and must specify how the data used for scoring are verified.
In the contract, the performance that was tendered and scored must be trackable during performance. To this end, the contract can specify the committed value, the data source, the method and frequency of measurement, who verifies the result and what happens if the committed performance is not achieved. Verifying the information in the tender supports the award. Measurement in operation shows whether the authority received the performance for which it awarded the points.
Before launching such a procurement, I would ask a question both of the procurement team and of those who will administer the contract. If in a year we are asked to show what has improved for the public service, what data will we put on the table? The answer should be found in the documentation, while we can still decide what we measure and who is responsible for verification.
Sources
- Procure Innovation EU. (2026, November 18). Insight No18: Green and digital transition through PPI (pp. 1–2) [PDF document]. Public Buyers Community. https://public-buyers-community.ec.europa.eu/system/files/2026-11/Insight%2018.pdf
- European Commission. (2021). Guidance on innovation procurement (2021/C 267/01). Official Journal of the European Union, C 267, 6 July 2021. https://eur-lex.europa.eu/legal-content/EN/TXT/?uri=CELEX%3A52021XC0706%2803%29
- Law No. 98/2016 on public procurement (Romania). Legislative Portal. https://legislatie.just.ro/Public/DetaliiDocument/178667
Reference
Slimac, O. (2026, November 19). How do we demonstrate that a public procurement has contributed to the green and digital transition? LinkedIn.
Editorial note
Published materials express the opinions and analyses of the authors who sign them and do not necessarily represent the position of Achiziții Corecte / Correct Procurement. Each author is responsible, in accordance with the law, for the content of their own contribution, including the statements made, the accuracy of information, the identification of sources, and respect for third-party rights. Publishing or making a material available does not constitute adoption or validation of all its opinions and conclusions. The materials are for information purposes and do not replace advice tailored to a particular situation. This note does not exclude liabilities that cannot be excluded by law.